Augmentation of Water Supply Scheme- Perinthalmanna 2007-2008

Date of SLSC Approval

:

03-01-2009 & 04-01-2009

Details of Administrative Approval

:

G.O (Rt) No: 2875/09/LSGD dated. 04-11-2009

Approved Cost

:

811.00 Lakhs

ACA Committed

:

648.80 Lakhs

ACA Received

:

648.80 Lakhs

State Share

:

81.10 Lakhs

ULB Share

:

81.10 Lakhs

Total Expenditure

:

1568.85 Lakhs (106.38 %)

Components of the Project

Components

Present Status

Progress as on- 31/10/14

Physical

Financial

Construction storage weir at Kattuppara

Work completed

100%

100%

Construction of 1.00 Lakh litre OHSR at Thekkinkode and laying clear water pumping main for zone

Work completed

100%

100%

Replacing 300 mm AC gravity main with 300 mm DI KP9 pipe from OHSR Pathaikkara to GLSR Kulirmala and Construction of 1.00 Lakh litr GLSR & pump house at Kunnappally

Work completed

100%

100%

Approach Road

Work completed

100%

100%

Supplying 2 nos of VT pump sets-180HP

Work completed

100%

100%

Supplying 6 Nos of C/F pumps- 150, 20 and 10 HP

Work completed

100%

100%

Laying PVC/GI for Zone 1&Zone3

Work completed

100%

100%

Do- Zone111,Zone4/Zone5

Work completed

100%

100%

Contingency Charges

Work completed

100%

100%